Prefab Project: 3rd- Party Fab
Project Manager: Matt Koenig
Fabrication Manager: Connor Johnson
Assistant Production Manager:  Wade Sullivan
VDC Lead: Mark Knudson
VDC Designer: Brock Flowers
ACP:  Mike Hansen

This week, Baer Manufacturing is currently focused on the construction of stub-up racks for a third-party project in North Dakota. These racks are being designed with a wall-mounted stand for structural support of the conduits. This stand ensures proper alignment of the conduits with the knockouts in the bottom of a custom pull box, which Baer Manufacturing is also responsible for designing and providing. In total, 64 of these stands are being manufactured for this project.